Engineering Economics — Quiz 3

Practice Engineering Economics — Quiz 3 on SonaPrep (Engineering Economics) with 10 scored questions. Use it to strengthen Engineering Economics skills with exam-style timing, clear scoring, and review after each attempt. Work carefully, check explanations for misses, then retake to track improvement before test day.
Questions
10
Category
Engineering Economics

Questions in this quiz (10)

  1. A project includes the following costs: $$120000$$ at time zero, $$12000$$ per year for years $$1$$ through $$6$$, and an additional $$30000$$ at the end of year $$4$$. Using a $$MARR$$ of $$9\%$$, what is the equivalent annual cost over the $$6$$-year period?

    • $$39,200$$
    • $$42,750$$
    • $$43,486$$
    • $$49,300$$
  2. An amount of $$15000$$ is invested today. The investment earns $$6%$$ annually for the first $$4$$ years and $$9%$$ annually for the next $$4$$ years. What is the future value at the end of year $$8$$?

    • $$24,560$$
    • $$25,880$$
    • $$26,733$$
    • $$29,100$$
  3. Two machines are being evaluated for a project. Machine $$A$$ costs $$45000$$, has annual operating costs of $$9000$$, a salvage value of $$6000$$, and a life of $$5$$ years. Machine $$B$$ costs $$65000$$, has annual operating costs of $$6000$$, a salvage value of $$10000$$, and a life of $$7$$ years. Using $$MARR=10\%$$, the equivalent annual cost of Machine $$B$$ is most nearly:

    • $$16,880$$
    • $$18,420$$
    • $$20,150$$
    • $$21,930$$
  4. A project requires an initial investment of $$100000$$ and generates annual net benefits of $$18000$$ for $$9$$ years. The salvage value is $$12000$$ at the end of year $$9$$. If the $$MARR$$ is $$11%$$, based on rate of return analysis, should the project be accepted?

    • Yes, because $$IRR\approx13.2%$$ which exceeds $$MARR$$
    • Yes, because $$IRR\approx12%$$ which exceeds $$MARR$$
    • No, because $$IRR\approx10.2%$$ which is less than $$MARR$$
    • No, because $$IRR\approx8.9%$$ which is less than $$MARR$$
  5. A concrete supplier has fixed costs of $$60,000$$ per month and variable costs of $$28$$ per cubic yard. If the company produces $$2500$$ cubic yards in a month, what is the total monthly cost?

    • $$98000$$
    • $$110,000$$
    • $$130,000$$
    • $$140,000$$
  6. A manufacturing plant reports total costs of $$220000$$ when producing $$5000$$ units and $$300000$$ when producing $$7000$$ units. Assuming a linear cost relationship, the variable cost per unit is most nearly:

    • $$30$$
    • $$35$$
    • $$40$$
    • $$45$$
  7. An engineering firm is considering investing $$100000$$ in a project that will return $$15000$$ per year. The firm could alternatively invest the money at $$8\%$$ annual interest. The annual opportunity cost of choosing the project is:

    • $$7000$$
    • $$8000$$
    • $$12000$$
    • $$15000$$
  8. A company allocates indirect costs based on direct labor hours. Total indirect costs are $$240,000$$. Department $$A$$ uses $$5000$$ direct labor hours, Department $$B$$ uses $$3000$$ hours, and Department $$C$$ uses $$2000$$ hours. The indirect cost allocated to Department $$A$$ is most nearly:

    • $$80,000$$
    • $$100,000$$
    • $$120,000$$
    • $$140,000$$
  9. Using the high-low method to separate mixed costs, a company observes total costs of $$340000$$ at $$8000$$ units and $$190000$$ at $$3000$$ units. The fixed cost component is most nearly:

    • $$80,000$$
    • $$100,000$$
    • $$120,000$$
    • $$140,000$$
  10. A precast concrete company has fixed costs of $$180000$$ per year. Each concrete panel sells for $$75$$ and has a variable cost of $$45$$. The number of panels that must be sold to break even is most nearly:

    • $$4000$$ units
    • $$5000$$ units
    • $$6000$$ units
    • $$7200$$ units

Loading quiz...