Quiz 7: FE Civil Ethics and Professional Practice

Free FE Civil ethics practice on PE licensure, NSPE and ASCE ethics, responsible charge, contracts, professional judgment, and engineering conduct.
Questions
10
Category
Ethics and Professional Practice

Questions in this quiz (10)

  1. According to most state licensing regulations, who is authorized to offer engineering services directly to the public?

    • A person who has passed the FE and PE exams but has not obtained a license
    • A licensed Professional Engineer with an active license in that state
    • An individual with a PhD in engineering from an accredited institution
    • A graduate of an ABET-accredited program with two years of experience
  2. What is the primary purpose of Continuing Professional Competency $$CPC$$ requirements for renewing a $$PE$$ license?

    • To meet the requirements of liability insurance providers
    • To generate income for licensing boards
    • To limit the number of practicing engineers
    • To ensure engineers continue developing and updating their professional knowledge and skills
  3. Under the $$NSPE$$ Code of Ethics, engineers are required to make public statements only:

    • When responding to media inquiries
    • In alignment with their employer’s position
    • With prior legal review
    • In an objective and truthful manner
  4. Which contract type assigns the greatest financial risk to the contractor?

    • Time and materials contract
    • Cost-plus-percentage contract
    • Lump sum contract
    • Cost-plus-fixed-fee contract
  5. Under professional ethics standards, what should an engineer do if asked to certify work that was not performed under their responsible charge?

    • Certify the work after performing a brief visual review
    • Refuse to certify work that was not completed under their responsible charge
    • Certify the work if it appears to comply with applicable codes
    • Certify the work while including a disclaimer about limited involvement
  6. In construction contracts, what is generally meant by the term substantial completion?

    • The project has reached at least half of its total completion
    • The project is fully complete with no remaining deficiencies
    • All payments to the contractor have been finalized
    • The work is complete enough to be used as intended, even if minor items remain
  7. According to the $$ASCE$$ Code of Ethics, how should engineers act in professional matters for each client or employer?

    • As independent parties without fiduciary responsibility
    • As advisors without binding obligations
    • As equal partners in decision making
    • As faithful agents or trustees
  8. In engineering ethics, what does the concept of $$professional\ judgment$$ require?

    • Engineers must rely on their knowledge, skills, and experience to make sound decisions within accepted standards
    • Engineers may disregard code requirements based on personal views
    • Engineers have complete and unlimited discretion in all situations
    • All decisions must be approved by a supervisor
  9. In an engineering contract, what is the purpose of a $$consequential\ damages\ waiver$$?

    • It removes all liability for the engineer
    • It prevents the client from ending the agreement
    • It excludes recovery for indirect losses such as lost profits, limiting damages to direct losses
    • It removes the need for professional liability insurance
  10. When serving as an expert witness in a legal case, an engineer should:

    • Support the position of the party who hired them
    • Provide impartial opinions based on professional expertise, regardless of who retained them
    • Refuse any payment to remain unbiased
    • Testify only in support of fellow engineers